Video: Student Activity Center Construction Progress & Tour

Project Updates

  • (February 9, 2018) - Center Grove hosts a public open house for the CGHS Student Activity Center. Click here to view photos.

    (January 22, 2018) - Center Grove opens the elevated walking track to White River Township residents during specific days/hours. Click here for details.

    (January 8, 2018) - CGHS PE classes begin using the facility as final touches to paint and trimwork on the facility continued into January.

    (December 21, 2018) - Flooring installation is complete in the Student Activity Center.

    (November 27, 2017) - New equipment installation is complete in the weight room. 

    (November 2, 2017) - Flooring installation is complete in the weight room. Installation is underway in the Student Activity Center. 

    (September 15, 2017) - The walking track that surrounds the perimeter of the Student Activity Center is complete. Installation is underway on the equipment and curtains that will hang from the ceiling, including volleyball nets, basketball goals, and wrestling mats. 

    (July 18, 2017) - Roofing was finished, along with the beams for the elevated walking track this spring. Much of the exterior of the structure was painted in late spring. This summer, electrical and HVAC equipment installation are underway, along with interior painting. Click here for 360 degree views of the construction progress.

    (March 17, 2017) - Roofing is being installed on the Center Grove High School Student Activity Center addition. In January and February, roof joists were put in place and concrete was poured in the restrooms, locker rooms, and new weight room spaces.

    (December 19, 2016) - Pre-cast panels in are in place to form the walls of the Center Grove High School Student Activity Center addition. The roof joists are scheduled to be installed in late December / early January.

    (October 7, 2016) - Construction began in August 2016 on a Student Activity Center for Center Grove High School. Much of the site work was completed in July, August, and September. In the next few weeks, pre-cast panels will be installed to create walls for the structure.

    (July 21, 2016) - Architect Bill Payne provided the School Board with an update on the design of the Student Activity Center. Click here to view the presentation.

    (May 25, 2016) - Construction on the Student Activity Center is expected to begin around the first of August and completed by November, 2017.

    (January 26, 2016) - Center Grove will move forward with the construction of a Student Activity Center addition to Center Grove High School (CGHS). The Johnson County Clerk announced Tuesday, January 26, 2016 that all signatures gathered during the remonstrance period had been reviewed. She reported that 67 percent of verified signatures gathered were in favor of the project. 
     
    The project will add 59,500 square feet of space to CGHS without increasing the tax rate for White River Township residents. The addition will serve a wide range of needs of the school’s more than 2,400 students and help alleviate the lack of gym and indoor practice/gathering space. The addition will also expand the current weight room to approx. 8,000 square feet. The weight room expansion will alleviate the safety concern created by the volume of students working in the current space constraints. The original concept for the space includes a multi-purpose floor, four basketball courts, and a 200-meter track. Read more >>