PLAYGROUND RENOVATIONS
SUGAR GROVE ELEMENTARY
TIMELINE
- July 19-28: Equipment removal, site work, installation of new equipment, concrete curbs
- July 24-31: Sub-base and poured in place
- After July 29: New Playworld equipment to be installed
Note: Sugar Grove will be the final project so as to not interfere with the Strawberry Festival in early June.