2018 BUDGET PREPARATION SCHEDULE
Scheduled | Actual | |
April 1, 2017 | 5/18/17 | Enrollment projections completed and reviewed by Superintendent’s Council |
April 15, 2017 | 5/18/17 | First draft of staffing decisions made by Superintendent’s Council and the Board |
June 29, 2017 | 6/29/17 | General Fund Revenue projections available |
July 1, 2017 | 7/24/17 | Business Office review of all budgets completed |
July 10, 2017 | 7/31/17 | First budget draft presented to Superintendent’s Council |
August 2, 2017 | 8/2/17 | First day of school for students |
August 25, 2017 | 8/25/17 | Budgets “closed” for further changes |
September 1, 2017 | 9/1/17 | Budgets transferred into the Gateway system |
September 7, 2017 | 9/7/17 | Turn budget advertisement in to the newspaper (Bus Replacement and CPF Plan only) |
September 11, 2017 | 9/9/17 | Publication of the proposed 2017 Bus Replacement Plan, CPF Plan, and Form 3 Levy Notice |
September 11, 2017 | 9/11/17 | All budget forms entered into Gateway system |
September 15, 2017 | 9/15/17 | Official ADM Enrollment Count Day |
September 21, 2017 | Public hearing of the proposed 2018 Budget, Bus Replacement Plan, and Capital Project Fund Plan | |
September 25, 2017 | All final budget forms posted in Gateway | |
October 26, 2017 | Proposed 2018 Budget, Bus Replacement Plan, and Capital Projects Fund Plan adopted by the Board at a regular meeting | |
October 30, 2017 | Publish Notice of Adoption of the Capital Projects Plan | |
November 1, 2017 | DLGF hearing | |
December 1, 2017 | Auditor certifies pay-2018 Assessed Values | |
January 1, 2018 | DLGF provides 1782 draft notice | |
February 1, 2018 | Final 2018 budget received | |
February 1, 2018 | Second ADM enrollment count day |