CENTER GROVE ELEMENTARY PROJECTConstruction began on June 2, 2014 and was completed in the Fall of 2015.Planned Renovations
- Addition of four classrooms
- Relocation of bus parking on south side of building to separate bus and car traffic for safety
- ADA upgrades and additional fencing at playground for safety and security
- 11,800 sq. ft. gym and office expansion
- Addition of secure vestibule at main entrance with office renovation
- Addition of new HVAC system
- Upgrade to electrical and data systems
- Upgrade to finishes throughout
- Renovation of old office area and gym/cafeteria area
Renderings, Floorplans, and Photos



-
Construction Cost
Budget $10,000,000 Groundbreaking & Ribbon Cutting CeremonyClick on the image below to see photos
from the May 5, 2014 event.Milestone DatesRelease for Bidding March 13, 2014
Receive Bids
April 10, 2014
Board Award of Contract
April 17, 2014
Notice to Proceed to Contractor
April 18, 2014
Complete Construction
December 2015