    CENTER GROVE ELEMENTARY PROJECT
    Construction began on June 2, 2014 and was completed in the Fall of 2015.
     
    Planned Renovations
    • Addition of four classrooms
    • Relocation of bus parking on south side of building to separate bus and car traffic for safety
    • ADA upgrades and additional fencing at playground for safety and security
    • 11,800 sq. ft. gym and office expansion
    • Addition of secure vestibule at main entrance with office renovation
    • Addition of new HVAC system
    • Upgrade to electrical and data systems
    • Upgrade to finishes throughout
    • Renovation of old office area and gym/cafeteria area

     


    Renderings, Floorplans, and Photos
     
  •  CGHS
      MSC
     MSN
     CGES
     MGES
     CGES
     Pleasant Grove
     Sugar Grove

  • Construction Cost
    Budget
    $10,000,000
    Groundbreaking & Ribbon Cutting Ceremony
    Click on the image below to see photos
    from the May 5, 2014 event.
     
    Milestone Dates
    Release for Bidding  March 13, 2014
    Receive Bids
     April 10, 2014
    Board Award of Contract
     April 17, 2014
    Notice to Proceed to Contractor
     April 18, 2014
    Complete Construction
     December 2015