SUGAR GROVE ELEMENTARY PROJECTSugar Grove received a secure vestibule at its main entrance and ADA updates to its playgrounds as part of the $1,680,000 project that includes Maple Grove E.S., Pleasant Grove E.S., Center Grove M.S. North, and Center Grove M.S. Central.
Construction Schedule- Construction began in June and was complete by the start of school on July 29, 2014.
- Construction began in June and was complete by the start of school on July 29, 2014.
-
SAFETY & SECURITY PROJECT UPGRADES(Project cost and dates include upgrades to Maple Grove E.S., Pleasant Grove E.S., Sugar Grove E.S., Center Grove M.S. Central, & Center Grove M.S. North)
Construction CostProject Budget
$2,000,000
Milestone DatesFebruary 6, 2014 Received Bids
February 20, 2014 Board Award of Contract
February 21, 2014 Notice to Proceed to Contractor
October 2014 Complete Construction