MAPLE GROVE ELEMENTARY PROJECTMaple Grove received ADA updates to its playgrounds as part of the $1,680,000 project that includes Pleasant Grove E.S., Sugar Grove E.S., Center Grove M.S. Central, and Center Grove M.S. North. Maple Grove was originally built with a secure vestibule at its main entrance.
-
SAFETY & SECURITY PROJECT UPGRADES(Project includes upgrades to Maple Grove E.S., Pleasant Grove E.S., Sugar Grove E.S., Center Grove M.S. Central, & Center Grove M.S. North)
CostConstruction Budget
Construction Estimate
$1,680,000 $1,030,000
Milestone DatesFebruary 6, 2014 Received Bids
February 20, 2014 Board Award of Contract
February 21, 2014 Notice to Proceed to Contractor
October 2014 Complete Construction