PLEASANT GROVE ELEMENTARY PROJECTConstruction ScheduleConstruction at Pleasant Grove was completed by Fall Break of 2014. Pleasant Grove received a secure vestibule at its main entrance, an upgrade to its front office space, and ADA upgrades to its playgrounds.
- Construction began in May.
- The front entry was closed over the summer, but reopened for the start of school on July 29, 2014.
- Front offices were relocated until the office renovation was completed during Fall Break 2014.
* Note: Pleasant Grove is receiving additional upgrades as part of a separate project.
- Construction began in May.
-
SAFETY & SECURITY PROJECT UPGRADES(Project cost and dates include upgrades to Maple Grove E.S., Pleasant Grove E.S., Sugar Grove E.S., Center Grove M.S. Central, & Center Grove M.S. North)
Construction CostProject Budget
$2,000,000
Milestone DatesFebruary 6, 2014 Received Bids
February 20, 2014 Board Award of Contract
February 21, 2014 Notice to Proceed to Contractor
October 2014 Complete Construction