    Center Grove M.S. Central received a secure vestibule at its main entrance as part of the $1,680,000 project that includes Maple Grove E.S., Pleasant Grove E.S., Sugar Grove E.S., and Center Grove M.S. North.

    Construction Schedule
    • Construction started in June and was completed by Friday, July 18.

  • SAFETY & SECURITY PROJECT UPGRADES
    (Project cost and dates include upgrades to Maple Grove E.S., Pleasant Grove E.S., Sugar Grove E.S., Center Grove M.S. Central, & Center Grove M.S. North)
     
    Construction Cost
    Project Budget
    $2,000,000

    Milestone Dates
    February 6, 2014  Received Bids

    February 20, 2014  Board Award of Contract
    February 21, 2014  Notice to Proceed to Contractor
    October 2014  Complete Construction

     
     
     
     
     
     